Notice to Mariners No 62 of 2025 (Temporary)
Thursday 18 September 2025
HARBORS AND NAVIGATION ACT 1993
Notice to Mariners No. 62 of 2025 (Temporary)
SOUTH AUSTRALIA – SPENCER GULF – LUCKY BAY – DREDGING OPERATIONS
Mariners are advised that dredging operations will commence in Lucky Bay from early October 2025 in an area bounded by the following coordinates:
- 33° 42’ 33.18” S 137° 02’ 15.78” E
- 33° 42’ 49.32” S 137° 02’ 41.88” E
- 33° 42’ 34.62” S 137° 02’ 54.54” E
- 33° 42’ 24.18” S 137° 02’ 36.12” E
Dredging operations are scheduled for up to 24 hours a day, 7 days a week and expected to be complete by the end of October 2025.
The discharge pipeline will rest on the seabed during normal operations; however, the pipeline may be floated to facilitate dredge movements. For which, a SÉCURITÉ warning will be issued on VHF channel 16.
The dredge will maintain a listening watch on VHF channel 16 and 1.
Mariners are advised to exercise caution when navigating in this area.
For further information please contact T-Ports at craigr@tports.com or by calling 0428 618 794
Charts affected: Aus 777, Aus 485, AUS 4060, AUS 4709
ENC: AU5LUB01
GORDON PANTON
Manager Marine Safety and Compliance
Department for Infrastructure and Transport
15 September 2025
DIT 2017/02277/01